Project Overview
Future Industrial Services (FIS) was contacted by a renowned multinational aerospace and defence company to assist with the decommissioning and removal of an on-site Pero degreasing machine. The complexity of the project led to the current on-site supplier declining the task, and we gladly stepped in to provide a solution.
Challenge
The Pero degreasing machine was located within a 6m x 4m x 3m steel framework, enclosed by steel panels. The machine consisted of stainless and copper hold vessels, pipework and a large stainless-steel drum, where Perchloroethylene was used to clean jet engine blades. Perchloroethylene is a highly toxic and volatile material, making it crucial to handle the decommissioning process with utmost care and safety.
Solution
Working closely with the customer, we devised a comprehensive proposal and a set of robust RAMS (Risk Assessment and Method Statement). The proposal was approved by the customer and their Quality, Health, Safety and Environment (QHSE) department, ensuring compliance and safety throughout the project.
Delivery
To ensure the safety of our team, our customer and the environment, we took several precautions during the decommissioning process. Our team of fully-trained Specialist Industrial Services operatives equipped themselves with full breathing apparatus safety equipment including air movers. All pipes, tanks and the drum of the machine were carefully disconnected to allow any residues to drain into a stainless-steel barrel.
To prevent any potential leaks or contamination, the
ends of each section of the pipe were sealed using a
double-bagging method. The tanks and drum were also placed into large bags and securely sealed. Once all internal components were safely removed, we proceeded to cut the steel framework and panels into manageable sections for removal from the building.
With safety a top priority, our Specialist Industrial Services team thoroughly jet washed and cleaned the floor area to ensure complete removal of any residual Perchloroethylene.
Safe & compliant Treatment & Disposal
Our Specialist Industrial Cleaning team took responsibility for the safe removal and disposal of the Perchloroethylene waste. The waste was transported to Augean’s facility at Kirkby where it underwent proper treatment. The tank containing the waste was then taken for high temperature incineration, ensuring complete elimination of any potential hazards.
Project Overview
Client: Multinational Aerospace and Defence Company
Project Name: Decommissioning a Pero Degreasing Machine
Project Scope: Specialist industrial services & disposal of hard to handle wastes
Project Highlights:
- Ability to accept and execute the works
- Works completed on time
- Project delivered within budget
- Customer received a rebate on the recovered metal
- Multi-site support across Augean and Future Industrial Services
Our team’s successful collaboration on this industrial cleaning and waste management project was a testament to the power of cross-functional working within the group. By drawing on the diverse skills and expertise of individuals from across various departments, we were able to tackle this complex challenge with a level of coordination and efficiency that surpassed expectations.
Lee Evans, General Manager - Industrial Services North West & Midlands