Background
This case study outlines the successful delivery of Augean’s first rooftop solar photovoltaic (PV) installation at its East Northants Resource Management Facility (ENRMF) near Kings Cliffe, Northamptonshire. The project forms part of Augean’s wider decarbonisation and energy efficiency strategy, aimed at reducing operational emissions, improving energy resilience, and supporting long-term sustainability objectives across its UK portfolio. Delivered in partnership with Ecovision Asset Management, the installation represents the first phase of a multi-site solar rollout, with additional deployments planned across 2026 and beyond.
Engineering & Design Approach
Ecovision Asset Management worked closely with Augean to develop a fully bespoke solution tailored to the structural and operational requirements of the ENRMF facility. Key integration features include:
- Coordination of mounting solutions.
- Structural load requirements.
- Waterproofing integrity.
- Optimal connection into the site’s electrical infrastructure.
This approach ensured safe installation within a live operational environment while delivering a robust, long-term energy asset.
Key success factors
- Strong collaboration between Augean and Ecovision Asset Management.
- Site-specific engineering design tailored to operational constraints.
- Safe integration within a live operational facility.
- Strategic alignment with long-term decarbonisation objectives.
The solar PV installation at ENRMF is an important milestone in our sustainability journey and demonstrates our commitment to delivering practical, long-term decarbonisation solutions across our operations. While this project will reduce our reliance on grid electricity, lower Scope 2 emissions and improve energy resilience, it is also just one part of our wider ESG roadmap. Across Augean, we are focused on increasing onsite renewable energy generation, improving energy efficiency, and continuing to invest in technologies that support the transition to a lower-carbon future. Through initiatives like this, we are strengthening operational resilience while making meaningful progress towards our long-term environmental and sustainability objectives
Gary Bower, Director of Corporate Stewardship
Scope
Design, installation, and commissioning of a rooftop solar PV system integrated into an operational facility.
Highlights
- First solar PV installation within Augean’s UK operational portfolio.
- ~90% on-site energy consumption, maximising efficiency, and cost savings.
- Reduction in Scope 2 carbon emissions and improved energy resilience.
- Bespoke engineering design tailored to a complex industrial rooftop environment.
Project Overview
The ENRMF solar PV system was successfully commissioned on 27 March 2026 and is now generating renewable electricity on-site. Designed specifically for a complex industrial rooftop environment, the system integrates seamlessly with ongoing site operations while maintaining high standards of safety, performance, and maintainability.
The installation directly offsets grid electricity demand, reducing both carbon emissions and operational energy costs. With approximately 90% of generated electricity consumed on-site, the system maximises efficiency and return on investment.
System Specification
|
Parameter |
Description |
Value |
|
Installed Capacity |
Total system output |
51.36 kWp |
|
Annual Generation |
Estimated yearly energy generation |
45,137 kWh |
|
On-site Consumption |
Energy used directly on-site |
40,623 kWh |
|
Self-consumption Rate |
Proportion of energy used on-site |
~90% |
|
Solar Modules |
High-efficiency PV modules installed |
96 × 535 W |
|
Inverter Capacity |
Total inverter output capacity |
40 kW |
Sustainability Impact
The system significantly reduces reliance on grid electricity by generating renewable energy on-site during daytime operations. This delivers:
- Reduced Scope 2 carbon emissions
- Lower operational energy costs
- Improved energy independence and price stability
- Increased readiness for future electrification initiatives, including EV infrastructure.
By maximising on-site consumption, the project ensures efficient use of generated energy while strengthening long-term sustainability performance.
Conclusion
The ENRMF solar PV installation represents a key milestone in Augean’s transition towards lower-carbon operations.
By embedding renewable energy generation into its infrastructure, Augean is reducing its environmental impact while improving operational resilience and energy security. The project provides a scalable model for future installations across its UK portfolio.
This case study demonstrates how collaboration between specialist renewable energy providers and complex industrial operators can deliver practical, efficient, and scalable sustainability solutions.